Inside the Burj Dubai - World's tallest building

|

Fact Sheet - Burj Dubai

Currently the worlds tallest building and tallest man-made structure, Burj Dubai is at the centre of Downtown Burj Dubai, the flagship mega-project of Emaar Properties in Dubai. The final height of the tower will be revealed on its completion in 2009.

With a development value of over US$1 billion, Burj Dubai, when completed, will fulfil all the criteria of the Council on Tall Buildings and Urban Habitat (CTBUH), which ranks the worlds tallest buildings on the basis of spire height, the highest occupied floor, roof height and pinnacle height.

At a current height of over 800 metres (2,625 ft), Burj Dubai has now also scaled over 160 levels, the most number of storeys in any building in the world. Burj Dubai has already surpassed the height of the KVLY-TV mast in North Dakota, USA - 628.8 metres (2,063 ft), which held the distinction of being the worlds tallest man-made structure. Burj Dubai is taller than Taipei 101 in Taiwan, which at 508 metres (1,667 ft) has held the tallest-building-in-the-world title since it opened in 2004. The tower also surpassed the 31-year-old record of CN Tower, which at 553.33 metres (1,815.5 ft) has been the worlds tallest free-standing structure on land since 1976.

Leveraging on the advancements in construction engineering, Burj Dubai undertook height enhancement in 2008 and is also upgrading its interior finishes. International designers from California have revisited the designs to make the residences more attractive and functionally superior.

In just 1,325 days since excavation work started in January, 2004, Burj Dubai became the tallest free-standing structure in the world. More than 11,000 consultants and skilled construction workers are employed on site, and the worlds fastest high-capacity construction hoists, with a speed of up to 2 m/sec (120 metres/min), were used to move men and materials.

When completed, the tower will have used 330,000 cubic meters of concrete, 39,000 metric tons of steel rebar and 142,000 sq m of glass and 22 million man hours.

The design inspiration for Burj Dubai is drawn from the desert flower, Hymenocalis, and incorporates patterning systems that are embodied in Islamic architecture. The tower is designed as three petals arranged around a central core. As the tower rises from the flat base, the petals setback in an upward-spiraling pattern.

Burj Dubais structure has employed the latest advances in wind engineering, structural engineering, structural systems, construction materials and construction methods. It will have a high performance exterior cladding system to withstand the harsh summer temperatures.

A mixed-use tower, Burj Dubai features 2 million sq ft of residential and over 220,000 sq ft of prime business space, in addition to the Armani Hotel Dubai, and Armani Residences Dubai, luxury hospitality ventures by Emaar in association with haute couture major Giorgio Armani S.p.A.

The tower offers recreational facilities and entertainment venues including four luxurious pools and a cigar club, a library, exclusive residents lounge, serviced residences, fitness facilities and an observatory deck on level 124, At The Top opening to impressive views of Dubai. The tower will also have a large Office Annexure.


Quick Facts:
Final Height: Unrevealed
No of floors: Unrevealed
Estimated population upon completion: 35,000
Developer: Emaar Properties PJSC
Architects and Engineers: Chicago-based Skidmore, Owings and Merrill (SOM)
Designer: Adrian Smith
Main Contractor: South Koreas Samsung Corporation
Project and Construction Manager: Turner International
Built-up area: 5 million sq ft
No of lifts to be installed: 54

Construction Schedule:
Excavation started: January 2004
Piling started: March 2004
Superstructure started: March 2005
Level 50: June 2006
Level 100: January 2007
Level 110 (tallest structure in the Middle East and Europe): March 2007
Level 120: April 2007
Level 130: May 2007
Level 141 (worlds tallest building): July 2007
Level 150 (worlds tallest free-standing structure): September 2007
Level 160 (worlds tallest man-made structure): April 2008
Cladding competed: September 2009


What is Burj Dubai?

What's at Burj Dubai?

Currently under construction - Burj Dubai is set to be the most prestigeous square mile of real estate on the planet! At its centrepiece stands the iconic Burj Dubai Tower, set to be the worlds tallest building upon completion in September 2009. This mammoth structure will be mostly residential; but will also be home to the worlds highest observation deck at a vertigo inducing 517m high, as well as the worlds first 6 star rated Armarni Hotel. Shadowed by the tower itself, across a massive man made lake will be home to the 'Supertall' Lake Hotel, the worlds largest ever shopping mall, over 70 highrise buildings and a beautiful 'old town' style village. All of the following will be finished by the end of 2009.

Current records

  • Tallest structure: 818 m (2,684 ft) (previously KVLY-TV mast - 628.8 m (2,063 ft))
  • Tallest freestanding structure: 818 m (2,684 ft) (previously CN Tower - 553.3 m (1,815 ft))
  • Building with most floors: 160 (previously World Trade Center - 110)
  • World's highest elevator installation

  • Worlds fastest elevators at speed of 64 km/h or 18 m/s (59 ft/s)[23] (previously Taipei 101 – 16.83 m/s)

  • Highest vertical concrete pumping (for a building): 601 m (1,972 ft) (previously Taipei 101 - 449.2 m (1,474 ft))

  • Highest vertical concrete pumping (for any construction): 601 m (1,972 ft)[24] (previously Riva del Garda Hydroelectric Power Plant - 532 m (1,745 ft)

  • The first world's tallest structure in history to include residential space

Note: Additional records for tallest skyscraper are considered unofficial. On 20 July

2007, the head of the Council on Tall Buildings and Urban Habitat (CTBUH), Antony Wood, said "We will not classify it as a building until it is complete, clad and at least

partially open for business to avoid things like the Ryungyong [sic] project. Taipei 101 is thus officially the world's tallest until that happens."

Timeline

  • 21 September 2004: Emaar contractors begin construction

  • February 2007: Surpasses the Sears Tower (since renamed to the Willis Tower) as the building with the most floors.

  • 13 May 2007: Sets record for vertical concrete pumping on any building at 452 m (1,483 ft), surpassing the 449.2 m (1,474 ft) to which concrete was pumped during the 

    construction of Taipei 101.

  • 21 July 2007: Surpasses Taipei 101, whose height of 509.2 m (1,671 ft) made it the world’s tallest building.

  • 12 August 2007: Surpasses the Sears Tower (Willis Tower) antenna, which stands 527.3 m (1,730 ft).

  • 3 September 2007: Becomes the second-tallest freestanding structure, surpassing the 540 m (1,772 ft) Ostankino Tower in Moscow.

  • 12 September 2007: At 555.3 m (1,822 ft), becomes the world's tallest freestanding structure, surpassing the CN Tower in Toronto.

  • 7 April 2008: At 629 m (2,064 ft), surpasses the KVLY-TV Mast to become the tallest man-made structure.

  • 17 June 2008: Emaar announces that Burj Dubai's height is over 636 m (2,087 ft) and that its final height will not be given until it is completed in September 2009.

  • 1 September 2008: Height tops 688 m (2,257 ft), making it the tallest man-made structure ever built, surpassing the previous record-holder, the Warsaw Radio Mast in 

    Konstantynów, Poland.

  • 17 January 2009: Topped out at 818 m (2,684 ft).

  • 1 October 2009: Emaar announces that the exterior of the building is completed.


Did You Know ?


  • Ten cranes and the world's fastest high-capacity constuction hoists - with a speed of upto 2m/sec (120m/min) are used to move men and material.

  • The building service/fireman's elevator will have a capacity of 5,500kg and will be theworld's tallest service elevator.

  • Burj Dubai will be the first mega-high rise in which certaib elevators will be programmedto permit controlled evacuation for certain fire or security events.

  • Parts of the tower reach upwards in a helical shape, with terraces, there are 26 intotal.

  • The Burj Dubai's observatory Elevators(double deck cabs) have a capacity for 21 personson each deck and will have the world's longest travel distance from lowest to highest stop.This Elevators will travel at 10 m/sec.

  • The Burj Dubai observation deck located 442 meters above groubd will be the highestpublicly accessible observation deck in the world.

  • The curtain wall of the Burj Dubai will be equivalent to 17 football(soccer) fields or 25American football fields.

  • The tower's peak electricity demand is estimated at 36 mVA, equivalent to roughly 360,000100-watt light bulbs all operating at the same time.

  • There will be 200 meters of spectacular dancing fountains at the foot of the BurjDubai.

  • When Completed, Burj Dubai will be the tallest building in the world in all fourcategories recognized by the Council on Tall Buildings and Urban Habitat(CTBUH), which compiles and ranks the world's tallest buildings.
  • The tower will house one of the first armani hotels.
  • Samsung Corporation from South Korea is the main building contractor.
  • The tip of the spire can be seen by a person 95 km (60 miles) away.
  • At the peak cooling times, the tower will require approximately 10,000 tons of cooling per hour, which is equivalent to the capacity provided by 10,000 tons (22.4 million ibs or 10.2 million kg) of melting ice in one day.

  • Burj Dubai will contain the world's highest elevator installation.
  • The amount of rebar used for the tower is 31,400 metric tons - laid end to end this would extend over a quarter of the way around the world.
  • The Burj Dubai's water system will supply an average of about 946,000 liters (250,000 gallons) of water per day.
 